A Pre-Bid meeting in connection with tender No. RBI/Kanpur/Estate/52/21-22/ET/67, which was floated on MSTC on August 05, 2021 for the captioned work, was conducted at 11.30 AM on August 27, 2021 at Conference Hall, 2nd Floor, RBI Kanpur. The said meeting was held following all COVID-19 protocols.

2. After welcoming all the members, Shri Bhaskar Choudhury (DGM, PMC) and Shri Nithin J Sebastian (A.M (Tech-Electrical)) explained tender documents and important timelines of the tendering process in brief and requested members to raise doubts, if any. Following queries/ doubts were clarified during the meeting:

S.No. Firm Name Query raised by firm Clarification
1) M/s S.S Associates The Retention/security money may be revised to 3 % from 5 % from recent Government’s Order. As per Bank’s internal circular the reduction in BG value (5% to 3 %) is not applicable to the tender for procurement of DG sets.
2) M/s S.S Associates Please Note in DG set Business almost all the manufacturer has sales and separate Dealers. Few Manufacturer are giving service them self after set is installed by the dealer. As procedure after installation the service will be supplied by separate service dealer appointed by company. Hence, NAMC may be deleted from the Bid. RBI may enter NAMC with service Dealer as soon as warranty/defect liability is over. This is current Trend in DG Business. Please Follow the tender.
3) M/s S.S Associates The client certificate Annexure B may substitute to competition certificate as no client has time to give so much of details. If RBI desired may cross check the worthiness of certificate. Please Follow the tender.
4) M/s S.S Associates The Banker’s certificate may be substitute to self-declaration as Bank has no time or this certificate not in manual Book. Please Follow the tender.
5) M/s S.S Associates The 5 years warranty for five components may be deleted as this is conditional and after 2 years warranty the engine is being taken care by RBI. Please Follow the tender.
6) M/s S.S Associates The factory testing in presence in RBI official is required or not. The factory testing by engineers may be avoided due to pandemic and test report and testing report of factory will work as final testing will be done at RBI site after installation. Factory testing will be conducted by RBI officials as per provisions mentioned in the tender.
7) M/s S.S Associates Payment terms may be modified as 85+10+5 as mostly manufacturer in not allowing any credit. Please Follow the tender.
8) M/s S.S Associates Testing: The 100 % and 110 % testing in works with door closed is not possible due to in take power uses by engine like radiator cooling Fan. Dynamo. The Testing as per ARAI will be done for two Hrs. Please Follow the tender.
9) M/s S.S Associates The specification of DG Set and Acoustics enclosure will be a per manufacturer only. As one DG the specification cannot be changed. Please Follow the tender.
10) M/s S.S Associates The fuel consumption will be a per manufacturer recommendation only. This is some time vary due to availability of fuel not available as per recommended grade. Please Follow the tender.
11) M/s S.S Associates The Microprocessor based controller supply with engine is capable for AMF/Manual operation. Please Follow the tender specifications.
12) M/s S.S Associates The cable Size of 2 *400 sq mm is much higher size. The Max 2*240 will be sufficient will be measured in single Run. The measuremen will be don on meer basis not in Run of 2 nos. Please Follow the tender.
13) M/s S.S Associates Control cable 2.5 sq* 16 c is much higher side, it should not be more the 2.5C*6 core. Please Follow the tender.
14) M/s S.S Associates The Exhaust pipe of C class is very very heavy is also not available may be amend to B class. The length is to be mention in BOQ. Please Follow the tender.
15) M/s S.S Associates The copper Plate earthing may be substitute to Pipe Earthing of 80mm x 3000 mts pipe. Please Follow the tender.
16) M/s Perfect House Pvt. Ltd. To include their ‘make’ which is not listed in the list of approved makes of DG sets. Not accepted by the Bank.

3. The meeting ended with thanks to all the members.

Note:

This document (minutes of the Pre-Bid Meeting) shall form a part of the tender.

  • Rest of the terms and conditions and specifications of the bid document shall continue to remain the same.

  • The above amendments/ clarifications are issued for the information of all the intending bidders.

  • The submission of bid by the firm shall be construed to be in conformity to the bid document and amendments/ clarifications given above.

Regional Director
RBI, Kanpur

August 27, 2021


List of participants

Sr No Name Designation
1 Shri Bhaskar Choudhury DGM (PMC-NZ)
2 Shri Nithin J Sebastian A.M (Tech-Electrical)
3 Shri Aquib Nawaz Assistant manager
4 Shri Apoorv Sachan J.E (Tech-Electrical)